Position of air distribution CAM of aluminum - plastic packaging machine
The installation sequence of the gas distribution CAM on the shaft: from the inside to the outside in turn for traction clamping cylinder CAM, stop cylinder CAM, molding blowing CAM and molding cylinder CAM. When the heat sealing CAM linkage heat sealing mold return point is lowest, the gas distribution CAM is installed at the position of installation.
Traction machinery in traction clamping cylinder machine control valve opened earlier.
When the traction machine is at rest, the check cylinder is clamped back.
After the forming die and blowing die are closed, the blowing CAM opens the machine control valve to blow forming.
The forming cylinder should rise synchronously with the heat sealing CAM.
The overall process is; Traction clamp clamp plastic sheet, plastic sheet positioning cylinder immediately released, the manipulator began to pull, the manipulator in place to stop, plastic sheet positioning cylinder pressed plastic sheet, forming cylinder and punching up work, traction clamp release, traction manipulator back, forming cylinder and punching down to the original position, this is to complete a cycle.